Lowering System 2500

Lowering System 2500

At the Tirreno Power plant in Vado Ligure Armofer is completing the lowering of the boilers thanks to its Lowering System technology, developed with Enerpac, capable of ensuring the safe descent of the iron giants. The system controlled by 2 control units reporting to the control unit located on the roof, is completed by Dywidag bars and allows the use of up to 24 hydraulic jacks simultaneously, each of which can support 103 tonnes of weight. All the data and procedures of the lowering cycle in the exciting video.